OLURE FIELD ALTERNATIVE CRUDE EVACUATION SYSTEM (ACES)

Project details

  • Client Multisub Energy Limited
  • Location Olure Field to MT Ultimate FSO, Ajapa, Nigeria
  • Timeline Completed
Contact Us

Project Overview

Multisub Energy engaged Dajo to execute an Alternative Crude Evacuation System (ACES) campaign from the Olure field to the MT Ultimate FSO offshore Ajapa. Dajo deployed the 3,300 DWT shuttle tanker MT Marina Express to complete the evacuation within a 20-day contract schedule.

Dajo managed end-to-end marine logistics, securing statutory clearances from the Nigerian Navy and the Nigerian Ports Authority (NPA). The scope covered offshore security escort coordination, vessel positioning, pumping operations, and zero-loss custody transfer reporting at the receiving terminal.

Delivery Metrics

40,000 bbls20 days3,300 DWT100%
Total crude volume evacuatedFull project delivery timelineMT Marina Express shuttle tanker capacityStatutory clearance and compliance rating