Project Overview
Multisub Energy engaged Dajo to execute an Alternative Crude Evacuation System (ACES) campaign from the Olure field to the MT Ultimate FSO offshore Ajapa. Dajo deployed the 3,300 DWT shuttle tanker MT Marina Express to complete the evacuation within a 20-day contract schedule.
Dajo managed end-to-end marine logistics, securing statutory clearances from the Nigerian Navy and the Nigerian Ports Authority (NPA). The scope covered offshore security escort coordination, vessel positioning, pumping operations, and zero-loss custody transfer reporting at the receiving terminal.
Delivery Metrics
| 40,000 bbls | 20 days | 3,300 DWT | 100% |
| Total crude volume evacuated | Full project delivery timeline | MT Marina Express shuttle tanker capacity | Statutory clearance and compliance rating |